NLSIU Campus Redevelopment 2025-2027

OVERVIEW

The existing NLSIU campus is set on 23 acres of land. The linear site approximately 900 metres in length, houses various academic, administrative and residential functions. Developed over a period of time (1991-present), the site is surrounded by various other institutional campuses.

We are now preparing for a significant phase of infrastructure upgrades to the University campus. These upgrades are an important step in shaping our academic and work space that better supports our future – a space more adaptable, collaborative, and aligned with how we work today, and how we aim to work tomorrow.

As part of the upcoming redevelopment on campus, this page will capture details on various aspects of the ongoing and planned infrastructural projects at NLSIU.

OAB Redevelopment

As part of the upcoming redevelopment of the OAB premises, the following key activities have been planned in a phased and systematic manner to ensure smooth execution while minimising disruption to existing operations:

1. Relocation of Faculty and Staff | Estimated Timeline: 01.06.2025 – 03.06.2025

To facilitate the Phase-1 redevelopment of the OAB building, faculty and staff currently occupying offices within the designated construction zone have been relocated to the Training Centre.

2. Temporary Shift of the OAB Canteen | Estimated timeline: 01.06.202 – 15.06.2025

Due to the demolition of the existing OAB canteen, a temporary dining facility has been set up at the Training Centre. The rear section of the Training Centre (adjacent to the pathway leading to the Health Centre) will be repurposed with appropriate seating arrangements to accommodate faculty and staff.

 

 

 

 

3. Barricading of Construction Zone | Estimated timeline: 27.05.2025 – 03.06.2025

Prior to the commencement of any demolition or construction work on campus, the designated areas are secured with appropriate barricading to ensure safety and prevent unauthorised access. The barricading layout is provided in the drawing attached below.

4. Demolition of OAB – Phase 1 | Estimated timeline: 01.06.2025 – 30.06.2025

Once relocation and safety preparations are complete, Phase-1 demolition of the OAB building will begin and is expected to take approximately one month.

 

5. Construction of New Faculty Block at OAB | Estimated timeline: 02.07.2025 – 30.06.2026

Following the demolition of the West and South-facing sections of the OAB building, construction of the New Faculty Block (NFB) will commence. The new OAB structure will consist of: Basement + Ground Floor + 5 Upper Floors + Terrace.

6. Demolition of OAB – Phase 2 | Estimated timeline: 01.07.2026 – 30.07.2026

After completion of the NFB Block, Phase-2 demolition will commence. This stage will involve partial removal of structures on the Ground floor, and the remaining eastern and northern sections of the OAB building. This phase does not involve any major demolition.

7. Redevelopment and Construction of New OAB Building | Estimated timeline: 01.08.2026 – 30.12.2026

Following the completion of all demolition activities, construction and redevelopment of the new OAB building will begin. This will be executed in parallel with renovation activities as part of the comprehensive campus enhancement plan. After completion, the redeveloped OAB building will significantly enhance infrastructure and academic capacity, comprising:
● 4 classrooms of 120-seat capacity
● 7 classrooms of 60-seat capacity
● 4 classrooms of 30-seat capacity
● 86 faculty rooms
● Redeveloped administrative block and other support spaces

NAB Redevelopment

As part of the upcoming redevelopment and construction of the NAB premises, a series of key activities have been strategically planned and will be executed in well-defined phases to ensure seamless progress while minimising disruptions to ongoing academic and administrative operations. This redevelopment aims to enhance classroom capacity and optimise space for various institutional needs.

1. Classroom Access Arrangement | Estimated timeline: 01.06.2025 – 15.06.2025

In view of the demolition of the existing NAB building’s south-facing section (commonly referred to as the pond side), alternate access routes to classrooms are being established for faculty and students from the library side.

2. Barricading Work | Estimated timeline: 01.06.2025 – 10.06.2025

To ensure safety during the demolition phase and construction activity, the construction zone will be secured with appropriate barricading.

3. NAB Construction Work | Estimated timeline: 01.08.2025 – 30.01.2027

The NAB work is expected to commence including major construction activities on the Pond Side in August 2025. After completion, the redeveloped NAB building will significantly enhance infrastructure and academic capacity, comprising:
● 4 classrooms of 120-seat capacity
● 12 classrooms of 60-seat capacity
● 4 classrooms of 30-seat capacity
● 55 faculty rooms
● Auditorium and other support spaces

The University is taking several measures to carry out these activities with minimal inconvenience. With the support of our community, we are confident of making NLS a future ‘living & learning’ campus. 